Support journalism that lights the way through the climate crisis

Goal: $100k
$11,845

A cryptocurrency firm has lost a bid to force BC Hydro to provide the vast amounts of power needed for its operations, upholding the provincial government's right to pause power connections for new crypto miners.

Conifex Timber Inc., a forestry firm that branched out into cryptocurrency mining, had gone to the B.C. Supreme Court to have the policy declared invalid.

But Justice Michael Tammen ruled Friday that the government's move in December 2022 to pause new connections for cryptocurrency mining for 18 months was "reasonable" and not "unduly discriminatory."

BC Hydro CEO Christopher O'Riley had told the court in an affidavit that the data centres proposed by Conifex would have consumed 2.5 million megawatt-hours of electricity each year.

That's enough to power and heat more than 570,000 apartments, according to data on the power provider's website.

Energy Minister Josie Osborne said when the policy was introduced that cryptocurrency mining consumes "massive amounts of electricity" by running high-powered computers around the clock, but adds "very few jobs" to the local economy.

In a statement released Monday, the company said it's "disappointed" with the court's ruling and is mulling an appeal.

"Conifex continues to believe that the provincial government is missing out on several opportunities available to it to improve energy affordability, accelerate technological innovation, strengthen the reliability and resiliency of the power distribution grid in British Columbia, and achieve more inclusive economic growth," the statement said.

Before the provincial government paused new power connections for cryptocurrency miners, BC Hydro released a report outlining the "conundrum" they represent to the utility provider.

Crypto mining company loses bid to force BC Hydro to provide #power. #BCHydro #BCPoli #ConifexTimberInc #CryptoMining

The report said power demand from cryptocurrency mining operations would challenge clean energy and electrification goals as adoption of things such as electric vehicles and heat pumps increase.

The report said bitcoin mining requires enough energy to power "a small country," and moratoriums on crypto mining in China, Algeria and some U.S. states "created a significant increase in demand for power in B.C. by cryptocurrency mining operations."

The court ruling said connection requests over the last few years from cryptocurrency miners in B.C. "far exceeded" BC Hydro's projections.

It said the pause ordered by the government was in response to "the very real prospect that devoting such a large proportion of the available electrical power supply to one industry would leave less energy for other uses which might result in increased costs to all other residential and industry customers in B.C."

This report by The Canadian Press was first published Feb. 5, 2024.

Keep reading

Kudos to the Court for refusing power to this crypto mining company. Due to Climate Change impacts (low water levels in reservoirs) BC Hydro doesn't have enough power to fulfill the needs of customers right now; we are importing power from Alberta and the US.

As the Climate Crisis worsens, we will need to ensure that BC Hydro and the BC Government don't allow anymore power service to these type of companies.

Of course, there is also the problem of LNG which will use huge amounts of power.

I'm no expert on this, but is anyone thinking about how Climate Change will affect our power supply? This issue was known years, if not decades, ago.

And apparently AI uses huge amounts of electricity....

Perhaps we need more incentives to encourage people to install solar panels on their rooftops.

Let the crypto currency bandits eat cake. Suggest they invest in wind and solar power to run their quasi criminal "mines". Same with all the other energy hogs.